Milestone - Date
Excavation - February 19
Rough Grade #1 - March 17
Lumber Drop - April 20
Vinyl Siding - May 6
Insulation #1 - May 12
Commit Closing - May 12 (the day we lock in my closing date)
Drywall Tape/Finish - May 13
Cabinet Install - May 28
Carpet Install - June 9
New Home Orientation - June 18
Customer Settlement and Sign off - June 23